mortise for Harrow Mutual and Eastgate Savings Day 1 of 365
mortise partners For the Joint Integration Committee
2 November 2026

Harrow and Eastgate, one bank by Day 365.

A twelve-month integration plan. Customers, colleagues and the regulator see one bank doing its job from the first Monday, and nobody hears about their branch from the local paper.

Engagement$7,800,000
Runs12 months
Day 11 Feb 2027
Harrow Mutualest. 1871 · 64 branches
Eastgate Savingsest. 1904 · 48 branches

What you told us in September.

Five people across two banks, four working sessions. These are their words, and the rest of this page answers them in order.

Harrow Mutual
“Our members joined a mutual. They'll want to know it still is one.”
Margaret, Chief Executive
“We can't have a single quarter where the regulator sees two sets of numbers.”
Dana, Chief Risk Officer
Eastgate Savings
“The app is the thing our customers love. Please don't take it away from them.”
Owen, Chief Executive
“Our core contract ends in March 2028. That's the real deadline, whatever the plan says.”
Rafael, Chief Operating Officer
“Our people are reading about this in the Saltmere Gazette.”
Nia, Head of People

Two charts, two maps, one bank.

Scroll and the two banks move together. Leadership on top, every branch below, drawn to the same scale.

Today. Two boards, two executive teams, 112 branches split between two names.

Harrow MutualEastgate SavingsThe combined bank
Harrow assets$9.2B
Eastgate assets$6.1B
Members410,000
Customers290,000
Colleagues1,750
Colleagues1,350

Together you're a $15.3 billion bank with 700,000 customers, 3,100 colleagues and 112 branches. Fifteen of those branches sit within a short walk of a branch from the other bank. What happens to them is the question your colleagues will ask first.

The combined bank on three dates.

Flip between them. Everything below redraws, from the branch map to the name above the door.

Harrow branchEastgate branchCombined bank branchBranch pair under review

One bank on paper, two on the high street.

Monday 1 February 2027

Customers notice almost nothing, which is the point. Cards, apps, branches and account numbers all work the way they did on Friday.

112branches
2names above the door
2core banking systems
2payrolls

    Five people sign this. Four questions decide it.

    Each chapter answers one question from the September sessions, written for the person who asked it.

    Equal on the day you sign, and still equal in year two.

    Twelve big choices were made in due diligence. Every one went through the same scored test, and both boards saw the scores before the vote.

    For Margaret, Chief Executive, Harrow Mutual, and Owen, Chief Executive, Eastgate Savings, on behalf of both boards.

    6from Harrow
    5from Eastgate
    1new to both
    The choiceWhat we keepFromScore
    Core bankingHarrow's platform, contracted to 2033 and already cloud-hostedHarrowH 84 · E 61
    Mobile appEastgate's app, rated 4.7 against 3.9EastgateH 58 · E 88
    Chair of the boardEastgate's chair, set in the merger agreementEastgateagreed
    Chief executiveHarrow's chief executive, set in the merger agreementHarrowagreed
    Head officeHarrow's Northgate buildingHarrowH 77 · E 70
    Operations centerEastgate's Leeming Street siteEastgateH 66 · E 79
    Card processorHarrow's, pending Eastgate's exit feeHarrowH 72 · E 69
    Contact centersEastgate's model, 84 percent of calls fixed first time against 71EastgateH 63 · E 81
    Savings rangeEastgate's five accounts replace Harrow's elevenEastgateH 59 · E 76
    Mortgage underwritingHarrow's rules and Harrow's teamHarrowH 80 · E 64
    Risk appetiteHarrow's framework, with Eastgate's climate limits addedHarrowH 75 · E 68
    The name above the doorStill open, see the questions belowNewdue Day 60

    One set of numbers from the first quarter-end.

    The regulator sees a single bank on 31 March 2027, eight weeks after Day 1. We rehearse that quarter-end twice before it counts.

    For Dana, Chief Risk Officer of the combined bank.

    • 18 Jan 2027Day minus 14
      Shadow quarter-end on the combined books

      Both finance teams close a fake quarter together. Every difference gets an owner before Day 1.

    • 1 Feb 2027Day 1
      One risk appetite statement in force

      Signed by the combined board on the close weekend, with Eastgate's climate limits carried across.

    • 31 Mar 2027Day 59
      First combined quarter-end

      One capital return, one liquidity return. A second dry run happens in the week before.

    • 11 May 2027Day 100
      Conduct review of the branch pairs

      Every one of the fifteen decisions is checked for customer impact before a colleague or customer hears it.

    • 19 Aug 2027Day 200
      Conversion readiness with the supervisor

      Two full rehearsals done, the third booked, rollback tested end to end.

    • 25 Sep 2027Day 237
      Core conversion weekend

      The supervisor has a seat on the go or no-go call. So do you.

    No system changes in a quarter-end week.Whatever the delivery date says. The plan already has room for it.
    Every cutover has a rehearsed way back.If we can't roll it back in a rehearsal, it doesn't go live.
    Every customer letter passes two readers.Compliance, then someone who's never worked in a bank.

    The weekend you become one bank, hour by hour.

    Legal completion runs from Friday 29 January to Monday 1 February. Drag through it and watch the five systems your team reports on.

    For Rafael, Chief Operating Officer of the combined bank.

    Fri 18:00Hour 0 of 62

    Doors close as two banks.

    Every branch shuts at the usual time. Eastgate runs its last end-of-day batch as Eastgate.

      Every colleague knows where they stand by Day 150.

      Percent of the 3,100 colleagues with a confirmed role, by date. Nobody waits for the last bar to hear the first thing.

      For Nia, Head of People of the combined bank.

      Day 1
      78
      Day 60
      86
      Day 100
      94
      Day 150
      100
      2,420 people hear on Day 1.Everyone in a branch or contact center is told their role doesn't change, by their own manager, before nine o'clock.
      Colleagues before customers.Each branch pair decision goes to the people in both branches a full week before any customer letter.
      The promise you've already made.Your joint statement ruled out compulsory branch redundancies in year one. The fifteen pair decisions are planned around keeping it.
      Eastgate's union, on its own clock.The 45-day consultation starts on Day 15, so role mapping is announced on time and by the book.

      One number for both boards.

      The integration office runs the whole year. The four workstreams are where your teams could take work back. Switch anything off and the total redraws.

      Integration office$3,400,000

      Workstreams$4,400,000

      We'd keep everything switched on. If something has to go, drop Branches and customers, because Harrow's marketing team rebranded 38 branches in 2019 without outside help. Keep Regulators whatever happens.

      Twelve months, Day 1 to Day 365.

      Three phases, sized to the work in them. The conversion weekend sits two months clear of Eastgate's core contract ending.

      Phase 1
      Day 1 to Day 100 · Feb to May 2027
      • 29 to 31 JanClose weekend
      • 1 Feb · Day 1One bank in law, two names on the street
      • 31 Mar · Day 59First combined quarter-end
      • 1 May · Day 90One payroll
      • 11 May · Day 100Leaders named, fifteen pair decisions shared
      Phase 2
      Day 101 to Day 240 · May to Sep 2027
      • JuneEastgate data mapped onto Harrow's core
      • Jul and AugThree full conversion rehearsals
      • 19 Aug · Day 200Readiness review with the supervisor
      • 25 to 26 Sep · Day 237Core conversion weekend
      Phase 3
      Day 241 to Day 365 · Oct 2027 to Jan 2028
      • Oct to DecCard reissue and one app
      • 15 Jan 2028One name on every branch
      • 24 Jan 2028Eastgate's old core switched off
      • 31 Jan · Day 365Handover to your teams

      Our readiness team has been with you since September under the planning letter. This proposal covers the twelve months after it.

      The terms, and what nobody knows yet.

      In plain language

      You pay monthly, by phase.

      Fees are billed at the end of each month for the phases and workstreams you've kept. No retainer up front.

      You can stop at the end of any phase.

      Thirty days' notice before a phase ends, no penalty. We hand over the plan, the risk log and every document in a state your team can run.

      The team is named and stays named.

      Hannah leads the engagement for the full twelve months. Nobody senior is swapped out without the committee's agreement.

      You own everything we make.

      Plans, run sheets, models and letters belong to the combined bank from the day they're written.

      Your auditors judge the success fee.

      If you choose it, your internal audit confirms each milestone. We don't mark our own homework.

      Open questions

      What's the combined bank called?

      The brand work assumes the boards decide by Day 60. If the name slips, the one-name date of 15 January slips with it, week for week.

      Needs a board decision by 1 April 2027
      What does leaving Eastgate's card processor cost?

      The exit fee isn't confirmed. A high number could make it cheaper to wait for renewal and move cards in Phase 3.

      Eastgate legal to confirm by 20 November
      Will the supervisor attach conditions?

      A capital condition on approval could move the first combined quarter-end. We've planned for one and can absorb it.

      Expected with approval in January

      Sign by 11 December and we're in the room on 29 January.

      By 20 NovemberThe committee reads this and sends questions. We answer them in writing within two days.
      By 4 DecemberBoth boards review the version you've built here, with the lines you've kept.
      By 11 DecemberFive signatures. Phase 1 planning starts the next morning.

      mortise partners · Hannah, Partner, leads this engagement A Closewell Studio example. Companies and figures are fictional.