HOLLOWAY BUILD / BID 2026-114

Floors 12 to 14, built in four phases.

A fixed-price fit-out for Selden Biomedical, sequenced so two floors stay open to staff for the whole build.

Selden BiomedicalIssued 31 October 2026, valid to 20 November

$3.0MFIXED PRICE

28 wkSITE SCHEDULE

2 of 3FLOORS STAY OPEN

SECTION, LOOKING NORTH

PHASE 2, WEEKS 7 TO 15
PHASE 1
PHASE 2
PHASE 3
HANDOVER
WK 14812162028
OUR WORKYOUR PEOPLESHEET A-00 OF A-12

Your brief had three sentences in it that mattered.

From the Selden Biomedical fit-out brief, issued 2 October. Everything after this page is built to answer them.

01
“Nobody loses a day at the bench.”

BRIEF SECTION 2.1, LAB OPERATIONS

Zero bench days lost.The new labs go in first, on 14. Your scientists leave 13 on a Friday and start on 14 on the Monday.

02
“The freezers and the cold room never go warm.”

BRIEF SECTION 2.4, SAMPLE STORAGE

Samples move once, and never leave the building.A temporary cold room on 14 takes them for two weeks, logged every fifteen minutes.

03
“Noise before six is a problem. After six we can live with it.”

BRIEF SECTION 3.2, WORKING HOURS

Every drill, core and cut is booked after 18:00.By day we frame walls and pull cable. The loud work waits for the labs to empty.

Holloway BuildSelden Biomedical, Levels 12 to 14Bid 2026-114A-01 Your brief

Drag through all 28 weeks.

Every Monday from 11 January to 19 July. Pick a week and see which floor we're building, where your people sit and what's happening that weekend. Drag the slider or the drawing itself.

SECTION A, LOOKING NORTH, LEVELS 11 TO 15

Week

9from Mon 8 Mar

We're building

Floors open

Seats today

Labs are on

This weekend

WK 17142128
Floor closed, we're buildingFour of your peopleWeekend movePlanned shutdown
Holloway BuildSelden Biomedical, Levels 12 to 14Not to scaleA-02 The 28 weeks

Why we start at the top.

We priced the job three ways. Here are all three, so you can check our working. Tap one to compare.

Holloway BuildSelden Biomedical, Levels 12 to 14Three sequences pricedA-03 The order

24 hours above the labs.

A Tuesday in week 4. We're building on 14 while your scientists work directly below on 13. Scroll to run the clock.

36 dBNoise at the bench, labs empty

The white line is your daytime limit, 55 dB

    The whole job, week by week.

    From your signature on 20 November to the last aftercare visit in July 2028. Tap any row for what happens in it.

    2026 to 2028
    PRE
    JANFEBMARAPRMAYJUNJUL
    AFTER
    11 Jan

    First day on site. Level 14 closes on Saturday 9 January, after the first move.

    4

    Weekend moves. Nobody packs on a weekday and nobody moves more than twice.

    7

    Planned shutdowns, all on Saturdays, every one listed in Teo's chapter.

    23 Jul

    All three floors handed back. Aftercare runs twelve months from there.

    Holloway BuildSelden Biomedical, Levels 12 to 14Programme rev CA-05 The programme

    Where does each team sit, every week?

    PPriya, Head of Workplace

    Pick a team. You'll see its floor in every phase and the exact Saturdays it moves. Seats open never drop below your busiest day, because we sized the temporary desks to your badge data from September.

    Seats open each week, against your busiest day of 255

    What could move the $3.0 million?

    DDaniel, Chief Financial Officer

    Most of it stays with us. Switch on anything you think could happen and see what reaches your budget. We'd suggest holding a $150,000 contingency, five percent of the price.

    If this happensWho paysCost to Selden

    On top of $3,000,000

    $0

    of a $150,000 contingency

    Per new seat

    $7,177

    Per site week

    $107,143

    What gets switched off, and when?

    TTeo, Facilities manager

    Seven shutdowns and four moves, every one on a Saturday. Tap a marked week for what goes off, for how long, and what we need from you. Tick them off as you book them.

    Your list

    0 of 7 booked

      What changes for you.

      For all 410 people who work on 12, 13 and 14. Press the floor you sit on today.

      Your floor today

      When we make noise, every weekday

      00:0006:00QUIET WHILE YOU WORK18:0024:00
      Do I have to pack my own desk?

      One crate each, handed out on the Wednesday before your move. Our movers do the rest, including screens and chairs. Your crate is waiting at your new desk on Monday.

      Will it be loud while I'm working?

      No. Anything louder than a normal office conversation happens between 18:00 and 06:00 or at weekends. If you hear a drill in the day, report it to Teo and we stop within ten minutes.

      Which lifts do the builders use?

      Only the goods lift at the back of the core. The passenger lifts, the main stair and the reception stay yours.

      What about the kitchen and the toilets?

      There's always a working kitchen and toilets on an open floor. When 12 closes in week 16, a temporary kitchen opens on 13 the same day.

      Holloway BuildSelden Biomedical, Levels 12 to 14Plain languageA-09 Everyone on 12 to 14

      Every line, and what it buys you.

      The three floors and the site team are the same in every version. What you're choosing between is how much protection the labs get. Our pick is the $3,000,000 version, with all five protections on and the faster programme off. Four weeks sooner is worth $148,000 only if you need the floors back for a reason we haven't heard yet.

      Fixed price, as configured

      $3,000,000

      Payments, monthly, less five percent retention

      Floors back

      Fri 23 Jul 2027

      Retention held

      $150,000

      Payments, monthly, less five percent retention

      Holloway BuildSelden Biomedical, Levels 12 to 14Bid 2026-114A-10 The price

      The terms, and what we don't know yet.

      Seven clauses in plain words, with the contract wording a tap away. Then four questions we can't answer today, each with the date it gets settled.

      7.01

      The price is fixed.

      The total you configured covers everything switched on. If we priced it wrong, that's our problem.

      Contract wording

      Lump sum, JCT Design and Build 2024 with Holloway amendments schedule R3. No fluctuations clause. Provisional sums limited to item PS1.

      7.02

      Changes are priced before they're built.

      Ask for a change and you get a written price within five working days. Nothing gets built until you say yes.

      Contract wording

      Change requests valued under clause 5, with a quotation period of five working days and no instruction to proceed without signed acceptance.

      7.03

      Loud work happens after hours.

      Quiet trades from 07:00 to 18:00. Drilling, coring and cutting from 18:00 to 06:00 and at weekends.

      Contract wording

      Working hours schedule WH1. Noise at the nearest occupied bench limited to 55 dB LAeq,15min between 07:00 and 18:00, with logging.

      7.04

      If we're late, we pay.

      $12,000 for every week past 23 July, up to ten percent of the price.

      Contract wording

      Liquidated damages at $12,000 per week or part week, capped at ten percent of the contract sum.

      7.05

      Five percent is held back.

      Half comes back at handover, the rest after twelve months of aftercare.

      7.06

      We come back fast.

      Any defect reported in aftercare gets a visit within 48 hours. Anything in the labs, within four.

      7.07

      We're insured for all of it.

      $10 million public liability, and contractor's all-risk cover for the full value of the works.

      Q1

      We haven't been above the ceilings on 13.

      We surveyed 12 and 14. On 13 the labs were running, so we didn't lift tiles. A $60,000 provisional sum covers old services we might find, and it sits outside the fixed price until we look.

      Settled Wednesday 2 December
      Q2

      The landlord hasn't approved the roof openings.

      The fume extract for the new labs runs up through the plant room. The landlord's engineer has the drawings. If approval slips, Phase 1 slips with it, a week for a week.

      Due Tuesday 15 December
      Q3

      The new cold room takes ten weeks to make.

      To have it on site in week 6 we have to order by 30 November, which is why we've asked for your signature by the 20th.

      Order by Monday 30 November
      Q4

      Your QA team may want longer to validate the labs.

      We've allowed five working days in weeks 5 and 6 before the scientists move. If your QA lead needs more, the move moves, and we'd rather know now.

      Ask your QA lead by 4 December
      Holloway BuildSelden Biomedical, Levels 12 to 14Bid 2026-114A-11 Terms

      Sign by 20 November and we're on site 11 January.

      That keeps the cold room order on time and the first move on the second Saturday of the year. Hannah, our project director, runs the job from signature to the last aftercare visit.

      Project

      Selden Biomedical, fit-out of Levels 12 to 14

      Bid

      2026-114 rev C

      Valid to

      20 Nov 2026

      Fixed price

      $3,000,000

      On site

      28 weeks

      Handover

      23 Jul 2027

      Contractor

      Holloway Build

      HOLLOWAY BUILD FOR SELDEN BIOMEDICAL

      A Closewell Studio example. Companies and figures are fictional.