Electrify all 160 buses within five years with no gap in service.Section 3.1
We swap buses by depot, a few dozen a year, and every new bus shadows its diesel for two weeks before the diesel retires.
See the depot mapElectrify all 160 buses within five years with no gap in service.Section 3.1
We swap buses by depot, a few dozen a year, and every new bus shadows its diesel for two weeks before the diesel retires.
See the depot mapKeep every route whole in the coldest weeks of winter.Section 3.4
Every route was checked against last January's low of minus 11. One needs a midday top-up, and it's already scheduled.
Test a routeUse every grant and utility program the district qualifies for.Section 4.2
We file the federal rebate, the utility make-ready program and the state workforce grant for you. They're shown under the total as offsets.
See the offsetsTrain our own drivers and technicians to run and repair the fleet.Section 5.1
172 drivers and 18 technicians, trained in your yards on your buses, with two of your technicians certified to train the next ones.
See the transportation chapterEvery line is a route. Grey runs on diesel today. Cyan runs on electricity. Drag the year or press play and watch the yards change, the chargers come online and the diesel bill fall.
Figures assume 12,800 miles per bus per year, 7 miles per gallon on diesel today and the grant amounts shown in the price. Change the buses per year in the price and this map follows.
Pick a route and drop the temperature. The bar shows what the bus can plan for after keeping a 20 percent reserve for detours and a heater running the whole way.
Each question is written the way you'd ask it in the hallway. Each answer is complete without a call.
No. That's the rule the whole plan is built around, and here's how it holds up in writing.
Yes, and it'll be quieter. Your drivers pull out the same way they do now. The difference is when buses fill up. Charging happens in the two windows your buses already sit still, and none of it touches the utility's 4 PM to 9 PM peak.
Spending follows deliveries, so no year carries more than its own buses and the chargers installed the summer before. The chart reads from the price below, so it changes when the configuration does.
If a rebate round is cancelled, we hold bus prices for 90 days after the announcement so you can move that year's order to the next round. Nothing is ordered on the strength of a grant you haven't been awarded.
We're replacing all 160 diesel school buses with electric ones over five school years.
The contract is $38,015,600, and grants should cover about $7.3 million of it.
Once every bus is electric, fuel and repairs cost about $1.4 million less each year.
Children ride the same routes, at the same times, with the same drivers.
You vote once, on December 9, and each year's order comes back to you as a consent item.
Reads aloud in about 40 seconds.
Change the buses per year, the chargers per depot or any option. The total updates, the grants recalculate and the depot map above follows.
What we'd sign if we were you. Keep the schedule as drawn and keep managed charging. It costs $1,174,000 over five years and avoids roughly $96,000 a year in demand charges at full fleet, so it pays for itself by the fourth year and keeps the yards off the utility's peak. If the budget has to come down, slow the 2031 order before touching chargers or grid work, because buses can wait a year and wiring can't be rushed.
It holds the 24-bus build slot for fall 2027. Build slots for 2027 close in January.
Twenty minutes, with Owen, our public fleets lead, and Teresa, the engineer who designed your depots.
Signed contract, year-one order placed, federal rebate application filed the same week.
Thanks. Owen will send the contract for $38,015,600 with your configuration attached and hold the board's December 9 slot. Nothing is ordered until the vote.
Questions before then go to Owen, public fleets lead at Voltcrest Mobility. He answers the same day.