Can it cost more than $142 million?
Priya, VP Finance
No. It's a guaranteed maximum price. If the build runs over, Thornbury pays the difference out of its own fee.
If it comes in under, Ashgrove keeps 60 percent of the saving and we keep 40. That's the only reason we'd ever want it cheaper, and it's a good one.
Drag a saving through the split
What happens if the final cost comes in under the guaranteed price.
When you pay it
Monthly, against work your cost consultant has checked. 5 percent held until final completion. Millions, by quarter.
Only three things can move the price
- A change Ashgrove asks for in writing. We price it within ten working days and nothing starts until you sign it.
- Ground worse than the June borehole survey. There's a $1.2M allowance inside the price for exactly this.
- The town's utility tie-in fee, if Merrow raises it above the $640,000 it quoted in August.
The September clause
If a bed isn't ready on September 1, 2028, Thornbury pays for that student's hotel room and a shuttle to campus until it is, up to $3.5 million. It sits on top of the standard delay damages.